Kialla’s Marlboro Dve will have changed traffic conditions from Tuesday, April 11 due to upgrade works.
Works are scheduled to commence between Kerang Ave and Archer Rd on Marlboro Dve from next week, with completion expected in late June — weather permitting.
The works will involve upgrades to the road, kerb, channel and drainage along with construction of footpaths and a roundabout at the Shiraz Dve intersection.
Marlboro Dve will be closed to through traffic from Kerang Ave to Archer Rd during this time. There will be limited access for residents of Marlboro Dve and connected streets.
Kerang Ave and other local streets can be accessed via Kialla Lakes Dve to the north side or Sanctuary Dve to the south side of the estate.
Greater Shepparton City Council requests that road users and pedestrians observe the detour signage and plan their trips to allow for the extra time required to travel.
Project updates can be found at https://greatershepparton.com.au/council/major-projects/marlboro-drive
For further information, contact council’s projects team on 5832 9700 or via email at projects@shepparton.vic.gov.au